Expansion subsidiary Rain

Our subsidiary in Rain has been being expanded with company parking spaces and additional areas for the logistics center. The production center with an integrated office area can cover higher capacities through the expansion and is therefore even set up more efficiently for the future.

Week 19

Our customers have unrestricted access to the office complex. Production and logistics continue undisturbed. At the Rain site, there are no problems with the construction work.

Week 18

Week 17

Week 16

The works continue: The casing for the foundations is largely prepared

Week 15

The exterior work on our site is continuing quickly: building materials are being delivered, the ground is being processed, dredging operations are in full swing

Preparation of the construction measures: excess material is removed and disposed of, the ground is leveled